Superior Pools

Pool Services

Outdoor living at its finest.

From the first sketch to the weekly skim — every service you need to build and keep a backyard you love.

What we do

Everything outdoors, under one roof.

Design

3D Pool Design

See it before we build it. Every curve and finish, rendered in 3D.

  • Photoreal renders
  • Material previews
  • Iterate live

Build

New Custom Pools

One-of-a-kind builds engineered for Florida living.

  • Freeform & geometric
  • Sun shelves & beach entries
  • Permits handled

Remodel

Pool Remodeling

Same footprint. Brand new pool.

  • Resurface & retile
  • Coping & deck refresh
  • Modern equipment

Spa

Hot Tubs & Spas

Daily-use spas — integrated or standalone.

  • Raised & spillover
  • Efficient heating
  • Custom seating

Features

Water Features

The sound of trickling water, tuned right.

  • Sheer descents
  • Bubblers & deck jets
  • LED night scenes

Care

Pool Cleaning

Weekly service that actually shows up.

  • Full-service visits
  • Chemistry logged
  • Equipment checks
The Process

From signature to first swim.

Eleven phases. Roughly 16–26 weeks total. Every step led by Superior crews — no subcontractors on the critical work.

1–2 wk
Design & Contract
3–8 wk
Permitting
8–12 wk
Construction
16–26 wk
Total From Signing
  1. Phase 01

    Design & Contract

    1–2 weeks

    Consultation, site visit, 3D rendering, selections.

  2. Phase 02

    Permitting

    3–8 weeks

    County submittal & approval. We handle the paperwork.

  3. Phase 03

    Site Prep

    1–3 days

    Sod scrape, walkthrough, yard ready for layout.

  4. Phase 04

    Excavation & Form

    2–4 days

    Stakes, dig to depth, laser elevations, stabilization rock.

  5. Phase 05

    Structure

    1–2 weeks

    #3 rebar grid, pre-plumb, gunite shell shoot & cure.

  6. Phase 06

    Plumbing & Electrical

    3–5 days

    Min. 2" Schedule 40 PVC, pressure tested, electrical rough-in.

  7. Phase 07

    Tile, Coping & Decking

    1–2 weeks

    Tile set by hand, footers, termite treatment, deck pour.

  8. Phase 08

    Equipment & Enclosure

    3–5 days

    Pad poured, pump/filter/heater set, screen cage erected.

  9. Phase 09

    Grade & Safety

    1–2 days

    Final grade, safety devices, county inspection.

  10. Phase 10

    Interior Finish

    1–2 days

    Plaster or pebble hand-troweled. Lifetime warranty.

  11. Phase 11

    Fill, Startup & School

    4–5 weeks

    Fill, 30-day soft startup, salt added, pool school.

Built for SW Florida

Pools here are different.

Nearly three decades and 10,000+ pools across Lee, Collier, Charlotte and Sarasota counties.

High Water Table

Sump system on every build to manage Florida groundwater.

Sandy Soils

Stabilization rock & compaction checked at multiple phases.

Coastal Materials

Every spec rated for salt air and saltwater exposure.

Hurricane-Ready

Equipment & decking meet or exceed FL Building Code.

Multi-County Permits

Lee, Collier, Charlotte & Sarasota — navigated daily.

30-Day Soft Startup

Our crew manages chemistry — we don't hand off and run.

Not sure where to start?

Tell us about your backyard — we'll come out, take a look, and put together a no-pressure plan.

Request a Free Estimate
Call Free Estimate